Reliable Controls

MACH-ProWebSys™​

Web Enabled Controller​

Publish your building automation system to the Web quickly and easily with the Reliable Controls MACH-ProWebSys. The first 3-in-1 device of its kind, the MACH-ProWebSys combines a BTL-listed BACnet Building Controller (B-BC), a BTL-listed BACnet Operator Workstation (B-OWS), and a powerful web server, all in a single package with an installed footprint of a typical building controller.

This is one of the most significant savings for Innotech clients and why Omni is so competitive. Omni’s Programmable Points allow every point on the controller to be used as any type of Input or Output, meaning you can use every point on the controller without waste, reducing costs by decreasing the number of controllers required on a project.

(Button will open link in new page)

Why Choose the Reliable Controls Platform?​

Compatibility
Backwards compatible to Legacy Reliable controls products first released
Bacnet (BTL Listed product)
Competitively priced
Streamlined Experience
Web controller has Web server built into controller to allow for graphics to be stored, eliminating the need for a headend computer.

Learn more about how IES and Reliable Controls can help deliver success for your next project

Justin Arnold

Managing Director
Justin has 22 Years experience in the construction industry specialising in electrical and controls design and installation for the HVAC&R industry. Justin spent 7 Years with Siemens Building Automation in Sydney as a controls technician programming & commissioning projects including data centres, hospitals, commercial developments and universities. During this time he gained a thorough understanding as to how multinational organisations operate, and effectively applies this knowledge to run an efficient, focused & streamlined business specialising in Building Automation Controls.

Bimberi Youth Justice Centre

Project Summary

Slider-3-1.jpg

This project consisted of thirteen high security state of the art residential, education & training, recreation, administration and other support facilities enclosed by a secure perimeter. The mechanical services in this unique project consisted of heating and chilled water plan, in-slab heating and VRV.
The BMS system is controlled via a central head end residing in the administration building. IES successfully delivered the project and continues to undertake the maintenance.

Highlights

Client

Hindmarsh

Location

Canberra City

Completion

2015

Technology
  • Reliance Controls….,
  • Automated backup power

28 Sydney Avenue

Project Summary

Slider-3.jpg

This project included not only the innovative 5 Star NABERS Energy rated office building construction but also an integrated fit-out. Mechanical systems include chilled and heating water systems utilizing water cooled chillers and gas fired boilers. Air systems include AHUs, FCUs, general ventilation systems and carpark ventilation and air quality monitoring system.

Using a High Level Interface the BMS communicates with chillers, VRF air conditioning system and Variable Speed Drives controlling pumps and fans. Remote monitoring of the BMS is possible via an ADSL connection using a web interface.

Highlights

Client

Hindmarsh

Location

Canberra City

Completion

2015

Technology
  • Reliance Controls….,
  • Automated backup power

One Farrell Place

Project Summary

the-cube

This project was carried out with 75% of the building tenanted. Controls were upgraded floor by floor until equipment in the roof-top plantroom was strategically replaced. Systems included all fan and pump motors replaced and controlled by new VSDs, new chiller and boilers.

The BMS controls all VSDs via HLI which means the BMS is able to access a wide range of information directly from the VSD over a single cable. Energy monitoring in the building is handled by the BMS and includes electrical meters and gas metering.

Highlights

Client

Benmax

Location

Canberra City

Completion

2015

Technology

– Reliable Controls….
– Automated backup power

Project: 212 Northbourne

Project Summary

Slider-3

T212 Northbourne Avenuehis project was undertaken to refurbish this unique buildings’ mechanical services plant to achieve a 4.5 star NABERS rating. The works included a full mechanical system upgrade including replacement of chilled, heating and condenser water systems.

Systems monitored include electrical meters, gas meters and water meters. A subsequent fit out was integrated into the base-building BMS with minimal re-engineering.

Highlights

Client

Benmax

Location

Canberra City

Completion

2015

Technology
  • Reliance Controls….,
  • Automated backup power